Project Description/Scope:

The project included construction of a standard design Training Support Center (TSC) approximately 72,200SF total.
Primary facilities include administrative offices and support spaces, classrooms, equipment maintenance and fabrication areas (approximately 23,600SF); warehouse Storage (approximately 48,600SF); covered storage areas and building information systems.

Design included Department of Defense Anti-Terrorism and Force Protection requirements.

The Mechanical Design included:

  • 92 well geothermal field
  • 2 - 40 ton packaged water to water heat pumps
  • 2- Chilled water pumps
  • 2 - Hot water pumps
  • 4 - Condenser water pumps
  • 21 - VAV's with HW reheat
  • 11 - Exhaust & Ventilation fans
  • 12 - Variable exhaust air volume box's
  • 1 - 15,000 CFM AHU
  • 1 - 2,690 CFM Heat recovery unit
  • 1 - 11,200 CFM Heat recovery unit

Project was designed around and achieved a LEED Silver Rating.


Location Fort Riley, KS
Client U.S. Army Corps of Engineers
Project Size 72,200 SqFt
MAWP Role Mechanical and Plumbing Design Build Contractor
Date Project Began June 2010
Actual Finish Date August 2011