Project Description/Scope:

Design Build Project to renovate BLDG 408 at Fort Riley, KS.

System was designed with a total of five Trane air handlers with variable frequency drives. 29 Variable Air Volume boxes, three Paterson Kelly high efficiency modulating condensing boilers, one 50 ton Trane condensing unit and a TAC DDC control system.

Preserving the historical integrity of the BLDG was a priority and was accomplished by minimizing duct and pipe penetrations though the original building structural stone walls.

Location Fort Riley, KS
Client U.S. Army Corps of Engineers
Project Size 16,800 SqFt
MAWP Role Mechanical and Plumbing Design Builder
Date Project Began April 2007
Actual Finish Date March 2008